Canals and Locks

How to dig your own river — surveying a level route, digging the channel and lining it watertight with puddled clay, feeding it with water, and climbing hills with pound locks and mitre gates. A single horse on a towpath pulls fifty tonnes; canals carried the coal, stone and grain of the first industrial age.

Difficulty
●●●●●
Time
Years. A small canal of a few kilometres with two or three locks is the work of a large community for several seasons
Steps from zero
13 prerequisites →

You need first

Surveying and LevellingStone Masonry

This unlocks

Dredging
The full path from nothing — 13 steps before this one
  1. Stone Tools
  2. Fire
  3. Finding and Preparing Clay
  4. Simple Machines
  5. Measurement from Scratch
  6. Writing and Numbers
  7. Quarrying and Cutting Stone
  8. The Kiln
  9. Arithmetic and Fractions
  10. Lime
  11. Surveying and Levelling
  12. Mortar and Concrete
  13. Stone Masonry
  14. Canals and Locks

Do them roughly in this order. See it on the tech tree →

Why it matters

Floating a load is the cheapest way to move it. A horse that carries about 120 kg on its back, and pulls about 2 tonnes in a wagon on a good road (Wagons and Carriages), can pull 30 tonnes on a river and about 50 tonnes on a still canal, at a walking pace, all day. Water carries the weight; the horse only has to overcome the water's drag, which is tiny at slow speed.

Rivers do this for free where they flow the right way, are deep enough and are not too fast (Boats and Sails). A canal is a river you build: level, calm, deep enough all year, and going exactly where you need it — from the coal pit to the town, from the quarry to the port. When the Duke of Bridgewater's canal reached Manchester in 1761, the price of coal in the city fell by about half. Within 70 years, Britain had more than 6,000 km of canals and improved rivers, and they carried the coal, iron, stone, clay and grain on which the Industrial Revolution was built.

The same skills — levelling over long distances, moving earth, sealing channels and controlling water with gates — also build Irrigation systems, mill races (The Watermill), reservoirs and harbours.

How it works

Level water

Water in a channel with no slope does not flow. A canal is a series of dead-level stretches, called pounds, like a staircase of long flat ponds. A boat crosses a pound with no current to fight in either direction.

When the land rises, the canal climbs from one pound to the next by a lock: a stone chamber with gates at each end, in which a boat is raised or lowered by filling or emptying the chamber.

1. Enter: chamber level with the lower pound, lower gates open 2. Close the lower gates, open the upper paddles: the chamber fills 3. Levels equal: open the upper gates and leave lower pound upper pound lower gates (open) upper gates paddle open rising Going down, the same steps in reverse: empty the chamber through the lower paddles.
Fig. 1 How a pound lock lifts a boat. 1: the boat enters the empty chamber through the open lower gates. 2: the lower gates close and water is let in from the upper pound through paddles; the boat rises. 3: when the levels match, the upper gates open and the boat leaves.

Why the gates point upstream

A gate holding back water takes an enormous push. The force on a gate grows with the square of the depth of water it holds back: for each metre of width, 1 m of water depth pushes with about 500 kg, 2 m with about 2 tonnes, and 3 m with about 4.5 tonnes. A lock gate 5 m wide holding back 3 m of water carries over 20 tonnes.

Mitre gates solve this. Each end of the lock has two gate leaves that meet in the middle at an angle, forming a shallow V pointing upstream — like the bow of a boat facing into the current. The water pushes the leaves together, so the higher the water, the tighter they seal. They also cannot be opened while there is any difference in level, which makes them safe: the water itself locks them.

The water budget

Every time a boat passes through a lock, a whole lockful of water flows down from the pound above. A narrow lock 22 m long, 2.2 m wide with a 2 m lift uses about 100 m³ — 100 tonnes of water — every time. On a busy canal with 50 boats a day, that is 5,000 m³ a day drawn from the top of the canal.

The highest pound, the summit, must therefore be fed with water: streams led in by feeder channels, and reservoirs that store winter rain for the dry summer. Planning the water supply is the first job, not the last. Many canals were built and then stood half-empty for want of it.

What you need

Item For a narrow canal
Boats Decide the boat first; everything else follows from it. A narrow boat 21 m long, 2.1 m wide, drawing 1 m loaded, carries 25–30 tonnes behind one horse.
Channel About 9 m wide at the water surface, 4.5–5 m at the bottom, 1.2–1.5 m deep, with sides sloping 1 up for every 1.5–2 across
Earth moved About 10 m³ for every metre of canal on flat ground — 10,000 m³ per kilometre — and far more in cuttings and embankments
Puddle clay Lining 60–90 cm thick on bed and sides wherever the ground is not naturally watertight
Locks Stone or brick chambers 22–23 m long and 2.2 m wide inside; gates of oak or elm
Masonry Dressed stone or brick (Stone Masonry, Bricks) and hydraulic lime mortar that sets under water (Mortar and Concrete)
Tools Spades, picks, wheelbarrows, planks for barrow runs, levelling instruments (Surveying and Levelling), carts, pumps for draining foundations (Pumps)
People A strong digger moves 7–10 m³ of easy ground a day; allow 1,000–1,500 worker-days per kilometre of simple canal

Where to find it

  • Puddle clay. Stiff, sticky, fine-grained clay that holds water — the kind that makes puddles last for days after rain. Dig a lump, wet it, and roll it into a thread: good puddle clay rolls to a thin thread without cracking. Avoid clay full of stones, roots or sand. It is often found under the topsoil along the canal line itself. See Finding and Preparing Clay.
  • Stone for locks, bridges and lining: hard, durable stone that does not crumble when wet (Quarrying and Cutting Stone).
  • Hydraulic lime comes from burning limestone that contains some clay; it sets under water (Lime, Mortar and Concrete). Lime from pure limestone will not set under water: add volcanic ash or crushed fired brick to it.
  • Gate timber: oak, or elm, which lasts for decades when kept permanently wet. Gates are made from heavy squared timbers, so choose big, straight trees.
  • Water: streams and springs that can be led into the summit pound, and valleys that can be dammed for reservoirs.

Step by step: planning and digging

  1. Survey the route. With a level (Surveying and Levelling), find a line that stays at one height for as long as possible — a contour canal follows the side of the hills round every valley, which is longer but needs no locks. Group the rises into a few places where locks can be built close together. Map where streams can feed the summit. Use Maps and Mapmaking to plan.
  2. Peg it out. Drive pegs every 20 m along the centre line, each marked with the depth to dig, so the finished water surface is dead level along every pound. An error of 10 cm along a pound means one end runs too shallow.
  3. Strip and dig. Remove the topsoil and keep it for the banks. Dig the channel to the planned shape — a trapezoid, wider at the top. Work from both ends of each stretch. Throw the spoil to the side to build the banks, and use the extra from cuttings to build embankments across low ground.
  4. Build the towpath bank. On one side, the bank is widened into a level towpath 2–3 m wide, for the horses. It should stand 50–60 cm above the water.
  5. Cross the streams. Where a stream crosses the line, carry it under the canal in a stone culvert — or, if it is to feed the canal, let it in over a stone sill.

Puddling: making the canal watertight

Sand, gravel, cracked rock and loose earth leak. A canal through them will drain itself in days. Puddling lines the channel with a thick, kneaded layer of clay and water that is almost perfectly watertight.

about 9 m at the water surface 1.2–1.5 m Puddled clay60–90 cm thick, kept wet Gravel coverprotects the puddle Towpath2–3 m wide, 50–60 cmabove the water Stone edgingwhere boats rub Seepage ditch Bankbuilt from the spoil natural ground
Fig. 2 The canal in cross-section. The channel is lined with a thick layer of puddled clay, protected by soil and stone where boats might scrape it. The towpath runs along one side; a ditch outside the bank catches any seepage.
  1. Prepare the clay. Dig it, break it up, and mix it with water — and in very sticky clay, a little sharp sand (about one part sand to three of clay) — until it is like stiff dough.
  2. Work it. Spread it in a layer about 15–20 cm thick. Then work it hard: cut through it again and again with spades, and tread it with heavy boots, or drive cattle back and forth over it, until it is a single smooth, plastic mass with no air pockets or cracks. This is the essence of puddling: unworked clay leaks; worked clay does not.
  3. Build it up. Add the next layer, working it into the one below so they become one. Build up 60–90 cm on the bed and the same against the sides, carried up the banks to at least 30 cm above the water line.
  4. Never let it dry. Puddle clay that dries shrinks and cracks, and it will never seal properly again. Keep it wet with water or cover it with damp earth while you work. Fill the canal as soon as you can.
  5. Protect it. Cover the puddle with a layer of soil, then gravel or stone at the edges, so boats' poles and horses' hooves and burrowing animals cannot pierce it. Line the banks at the water line with stone or timber where boats will rub.

Tip The clay-trough test. Make a small trough of puddled clay, fill it with water and leave it for a few days. Good puddle loses nothing but what evaporates. James Brindley, the great canal engineer, is said to have shown a committee of Parliament exactly this.

Step by step: building a lock

High waterpresses the leavestogether UPPER POUND LOCK CHAMBERlow water to the lower gates Mitrethe V points upstream Heel post Balance beampush to swing the gate Sillstone V on the floor Gate openfolds into a recessin the wall
Fig. 3 Mitre gates seen from above. The two leaves meet at an angle pointing upstream, against a stone sill on the chamber floor. The higher water presses them shut. The long balance beams give the leverage to swing them, but only once the levels on both sides are equal.
  1. Foundations. Dig the lock pit down to firm ground, well below the bottom of the lower pound. Keep it dry with pumps (Pumps). On soft ground, drive timber piles and lay a timber platform. Make the floor (the invert) of masonry curved slightly upward like an upside-down arch, so the water pressure under it cannot lift it (Arches, Vaults and Domes).
  2. The chamber walls. Build them of stone or brick in hydraulic lime mortar, about 1.2–1.5 m thick at the base, thinning toward the top, with puddled clay rammed behind them to keep water from leaking round. Typical chamber: 22–23 m long, 2.2 m wide inside for narrow boats (4.5 m or more for wide barges), with a lift of 1.5–3 m.
  3. Gate recesses and sills. At each end, build a recess in each wall into which the open gate leaf folds flat. On the floor, build a stone sill (cill) in the shape of a shallow V pointing upstream, against which the bottoms of the closed gates press.
  4. Make the gates. Each leaf is a frame of heavy oak or elm: a thick upright heel post that turns in a stone hollow at the bottom and a strap at the top, a mitre post at the free edge, and horizontal rails between, planked over on the upstream face. A long balance beam — a heavy timber reaching out over the bank — counterweights the gate and gives leverage to push it open. Set each leaf at about 18–20° from straight across the lock, so the V is about one-sixth of the lock's width deep — about 35–40 cm for a 2.2 m lock.
  5. Paddles. In the lower part of each gate, fit sluices: openings about 30–45 cm square, closed by sliding wooden boards (paddles). They are raised by a rack (a toothed bar) and pinion (a small gear) turned with a removable crank handle called a windlass, and held up by a ratchet catch (Gears). Bigger locks also have ground paddles: culverts through the walls round the gates.
  6. The overflow. Beside each lock, build a bywash: an open stone channel that lets surplus water spill from the upper pound to the lower without flooding over the gates.

Working a lock (going up)

  1. Check the lock is empty (level with your pound). If not, close the upper gates and paddles and open the lower paddles to empty it.
  2. Open the lower gates, bring the boat in, and close them behind it.
  3. Close the lower paddles. Open the upper paddles slowly — a little at first, then fully. The boat rises. Keep it held toward the back of the chamber with a rope so it is not thrown against the upper gate by the inrushing water.
  4. When the levels are equal, open the upper gates and take the boat out. Close the gates and paddles behind you.

Going down, do the same in reverse. Always close all paddles and gates when you leave, or the upper pound will drain.

Supplying water

  • Feeders. Lead streams into the summit pound by contour channels, with a weir to send surplus away in floods.
  • Reservoirs. Dam a side valley (Dams and Reservoirs) above the summit level to store winter water; release it through a sluice in dry months. An earth dam needs a puddle-clay core, carried down into firm ground, and a stone spillway able to carry the biggest flood — an earth dam overtopped by water will wash away.
  • Overflow weirs along every pound let flood water out before it tops the banks.
  • Side ponds and pumping. Where water is short, a side pond beside a lock saves part of each lockful, and later engineers pumped water back up with The Steam Engines or The Windmills.

How to tell it worked

  • Hold the water. Fill a finished pound and mark the level on a post. It should drop no more than a centimetre or two a day in dry weather (evaporation). More means a leak.
  • Find leaks. Look for wet, soft or unusually green patches on the outside of embankments, springs at their foot, and small whirlpools in the water above. Stop them at once by dumping puddle clay into the water at the spot.
  • The lock. It should fill or empty in 5–10 minutes. Closed gates should leak only a little at the mitre; a closed upper gate that shows a steady stream of water through the sill needs re-seating.

Note Troubleshooting. Water level keeps falling → leaking puddle. Drain the stretch, find the soft wet place, dig out the faulty puddle and re-puddle it, working the new clay well into the old. Gates will not open → there is still a difference in level; open the paddles fully and wait. Never force a gate with a lever. Gates do not seal → silt, a stone or a branch is caught on the sill. Lower a pole along the sill to clear it. Boats ground halfway along a pound → the bed is uneven or silting; check it with a sounding pole and dredge (Dredging). Banks slump → the sides are too steep for the soil; cut them back to a gentler slope and protect the water line with stone.

Dangers

Danger Locks drown people. The chamber walls are sheer and slimy and there is nothing to hold; the water near open paddles boils and pulls a swimmer under. Never open paddles while anyone is in the water. Keep children away from locksides. Fit iron ladders or footholds in every chamber wall, and keep a long pole and a rope at every lock (rescue methods in Life Jackets, Lifebuoys and Lifeboats).

Danger Embankment and dam breaches. A canal embankment or reservoir dam that fails releases a wall of water onto the land below. Walk the banks regularly, act at once on any leak, never let a reservoir overtop, and do not build houses at the foot of a reservoir dam.

  • Collapsing cuttings and lock pits. Deep excavations in soft ground can cave in on the diggers. Slope the sides back or shore them with timber (Mining and Tunnelling).
  • Swinging balance beams and windlasses. A windlass left on a paddle spindle can spin back and break an arm if the catch slips. Never let go of it while the paddle is up; remove it as soon as the catch is on.
  • Ice. In winter, canals freeze. Thin ice over still canal water looks safe and is not.

What this unlocks

Canals bring coal (Coal and Coke), iron ore and limestone together to make The Blast Furnace and Cast Iron and Steel in Quantity, carry bricks, lime and stone to growing towns, and take grain and goods to market. The same engineering — surveying, cuttings, embankments, aqueducts, tunnels (Tunnels and Rock Drilling) — was taken over directly by the builders of Railways, which eventually replaced canals for most traffic. Steam tugs (Steamships) later towed trains of barges. Canals remain the cheapest way to move heavy, slow cargo where water allows.

How it was first done

China's Grand Canal, the longest in the world at about 1,800 km, was joined into one system under the Sui dynasty around AD 605–610, from older sections, some dug in the 5th century BC. The pound lock with two gates was invented in China by the official Qiao Weiyue in AD 984, to stop barges being wrecked at the old single-gate "flash locks". In Europe, pound locks appeared in the Netherlands and Italy in the 1300s and 1400s, and mitre gates are credited to Leonardo da Vinci, who worked on the canals of Milan in the 1490s.

France's Canal du Midi (1666–1681), built by Pierre-Paul Riquet, crossed southern France with 240 km of canal and 63 locks, and solved the summit water problem with the great Saint-Ferréol reservoir. In England, the self-taught engineer James Brindley built the Duke of Bridgewater's canal (opened 1761) using puddled clay, starting the British canal age. The Erie Canal in New York (1825), 584 km long with 83 locks, opened the American Midwest to trade and made New York the country's greatest port.