Surveying and Levelling

How to measure the land — distances with ropes and chains, straight lines and right angles, how much higher one place is than another, and the width of a river or the height of a cliff you cannot reach. Without surveying, water will not flow down your channels and tunnels will not meet.

Difficulty
●●●●●
Time
A day to make the tools; an afternoon to level a few hundred metres; a season to map a valley
Steps from zero
3 prerequisites →

You need first

Measurement from ScratchArithmetic and Fractions

This unlocks

Dams and ReservoirsPipes, Plumbing and AqueductsField Drains, Terraces and Erosion ControlMaps and MapmakingCanals and LocksRoads and Bridges
The full path from nothing — 3 steps before this one
  1. Measurement from Scratch
  2. Writing and Numbers
  3. Arithmetic and Fractions
  4. Surveying and Levelling

Do them roughly in this order. See it on the tech tree →

Why it matters

Water runs downhill — but only if "downhill" is really downhill. An irrigation ditch, a drain, an aqueduct or a sewer that falls 2 m in a kilometre works; one with a hidden hump in the middle floods its upper end and runs dry below. Across a field the eye cannot tell the difference. Surveying is the craft of measuring the land so exactly that you can lay out a house square, a ditch at the right slope, a road around a hill, or a tunnel dug from both ends that meets in the middle.

Every large work in this book needs it: Pipes, Plumbing and Aqueducts and aqueducts, Sewers and Wastewater, Irrigation, Field Drains, Terraces and Erosion Control, Canals and Locks, Roads and Bridges, Railways, Foundations and Floors, and Mining and Tunnelling and tunnels. And a careful survey drawn on paper is a map — see Maps and Mapmaking.

How it works

All surveying measures just three things:

  1. Distance — how far, along level ground.
  2. Direction — the angle between one line and another.
  3. Height — how much higher or lower one point is than another.

Two ideas make it possible with simple tools.

  • Still water is level and a hanging weight is vertical. Every level in history, from Roman to modern, is built on one of these two facts.
  • Similar triangles. Two triangles with the same angles have their sides in the same proportion. So you can measure a small triangle you can walk around and work out a big one you cannot. That is how you find the width of a river or the height of a tower. See Geometry and Trigonometry.

The enemy is error that adds up. A level that is off by a millimetre per metre makes a 10 cm mistake over 100 m. So every method here includes a check: measure twice in opposite directions, turn the tool end-for-end, or walk a loop back to where you started.

What you need

Tool Make it from For
Pegs Hardwood, 30–40 cm, pointed Marking points
Ranging poles, 3 or more Straight poles 2 m long, painted in 50 cm bands of red and white (ochre and lime) Seeing a straight line from far away
Measuring rope or chain See below Distance
Plumb line A stone or lead weight on a thin cord Vertical
A level Water tube, chorobates or sighting level (below) Height
Levelling staff A straight board 3 m × 6 cm × 2 cm, marked in cm Reading heights
3–4–5 rope or groma Cord, or a wooden cross with four plumb lines Right angles
Plane table A flat board on a tripod, paper, a ruler with sights Mapping, angles
Field book Paper and Ink, or a wax tablet Writing every reading at once

The units of length come from Measurement from Scratch.

Where to find it

Measuring distance

Pacing. Count your steps over a measured 100 m, three times, and average. A typical adult double pace (left foot to left foot) is about 1.5 m. Pacing is good to about 1 part in 50 — fine for a first look, not for building.

Rope. Stretch-test a long cord: hang a 20 kg stone on it for a day, then mark it. Mark every metre with a knot or a dab of paint and every 5 m with a coloured tag. Wet rope shrinks; dry rope stretches. Check it against your standard rod every day you use it.

Chain. Better: a 20 m chain of 100 links of stiff iron wire, each 20 cm from ring centre to ring centre, with brass or bent tags every 2 m and a handle at each end. A chain does not stretch with weather. (The old English Gunter's chain of 1620 was 66 feet long with 100 links; ten square chains made an acre.) Two people use it:

  1. The leader walks ahead with the front end and ten iron arrows (marker pins); the follower holds the back end on the start and lines the leader up by eye with a ranging pole at the far end.
  2. The chain is pulled taut, not jerked, and the leader pins an arrow at its end.
  3. Both walk on; the follower picks up each arrow in passing. The arrows in the follower's hand count the chains.

On slopes, distances are measured level, not along the ground. Measure downhill in short steps: hold the chain level (check with a small level or by eye against the horizon) and drop a plumb line from the raised end to the ground.

Check: measure every important line twice, once in each direction. With care, a chain gives 1 part in 1,000 (10 cm in 100 m) or better.

Straight lines and right angles

Lining in. Plant ranging poles at both ends of a line. Stand behind one and look past it at the other; wave a helper with a third pole left or right until all three poles are hidden behind each other. Repeat for as many points as you need.

The 3–4–5 triangle. A rope loop with 12 equal spaces pegged into sides of 3, 4 and 5 makes an exact right angle (see Measurement from Scratch). For buildings, use the chain: 6, 8 and 10 m, or 9, 12 and 15 m.

The groma. The Roman surveyor's tool: a pole about 2 m tall carrying a horizontal wooden cross, with arms about 50 cm long, and a plumb line hanging from each of the four tips. Set the pole upright over your point. Sight past two opposite plumb lines to fix one line; sight past the other two and you are looking along an exact right angle. Check it by turning the cross a quarter turn and sighting again.

Laying out a building.

  1. Peg one long side.
  2. Set out right angles at both ends with 3–4–5 and peg the short sides.
  3. Measure the fourth side and check that the diagonals are equal — if they differ, the corners are not square.
  4. Set profile boards (horizontal boards nailed to two stakes) about 1 m outside each corner. Stretch strings between nails on them to mark the wall lines. You can then dig the foundation trenches without losing the lines (see Foundations and Floors).

Levelling

Chorobates (water table level) Water-tube level about 6 m long Water groovelevel when water iseven at both ends Plumb lineshang on the red marks Sight along the topto a staff 20–30 m off Same heightat both ends Clear endsglass or horn Tube: gut or leather hoseno air bubbles, ends left open
Fig. 1 Two simple levels. The chorobates (described by the Roman engineer Vitruvius) is a long wooden bench, levelled with plumb lines or a groove of water; you sight along its top. The water tube works because water stands at the same height in both open ends, however the tube winds between them.

The levels

The water tube. The simplest and, over short distances, the most accurate. A long tube — cleaned gut tied end to end, a greased leather hose, or reed lengths joined with sleeves — with a clear end at each end: a short Glass tube, horn scraped thin enough to see through, or simply the open end held upright. Fill it slowly until no bubbles remain. Hold one end at a mark on a post and raise or lower the other beside a second post until the water at the first end stands exactly on its mark; the water at the second end is then at the same height. Good to a few millimetres over 20–30 m, even round corners — ideal for floors, foundations and building corners.

The chorobates. Vitruvius, writing in the 1st century BC, preferred it to all others: a straight beam about 6 m long, on four legs, with diagonal braces. A vertical line is cut on each brace; when plumb lines hanging from the top beam fall exactly on those lines, the top is level. In wind, use a groove cut along the top — about 1.5 m long, 2 cm wide, 3 cm deep — filled with water: when the water touches both ends of the groove evenly, it is level. Sight along the top edge to a staff some distance away.

The sighting level. Lighter and faster: a straight bar about 1 m long on a tripod, with a small sight at each end (a thin vane with a pinhole at one end, a vane with a fine thread or slit at the other), set level by a plumb line hanging on a mark, or later a spirit level — a slightly curved glass tube almost filled with alcohol (see Distillation), whose bubble rests at the middle when the tube is level. Add a The Telescope with cross-hairs and you have a surveyor's level.

Test and adjust any sighting level by the two-peg test:

  1. Drive two pegs 40–60 m apart.
  2. Set the level exactly halfway between them and read the staff on each. The difference is the true difference in height, because any tilt of the sight line affects both readings equally.
  3. Move the level close to one peg (3 m away) and read both again. If the difference is not the same, the sight line tilts. Adjust the plumb-line mark (or the bubble) until it is, and test again.

The levelling staff

A straight board 3 m long, marked in centimetres from its foot, with every 10 cm painted alternately red and white so the reader at the level can count them from 30 m away. Number every 10 cm. The helper holds it vertical — rock it slowly toward and away from the level; the lowest reading you see is the right one.

Levelling a line

20–50 m the same distance Level 2.33 m backsight 1.24 m foresight Peg Aknown height Peg Bnew point B is higher than A by 2.33 − 1.24 = 1.09 m Then move the level past B: B's reading becomes the next backsight.
Fig. 2 Levelling from A to B. The level's line of sight is horizontal, so the difference between the two staff readings is the difference in height of the ground. Keeping the two sight distances equal cancels any small error in the level.
  1. Hold the staff on the starting point A, whose height you know (or call it 100.00 m).
  2. Set the level up about halfway to the next point, no more than 50 m from each staff. Read the staff on A: the backsight.
  3. The staff moves to the next point B. Turn the level and read it: the foresight.
  4. Backsight minus foresight = rise (if positive) or fall (if negative) from A to B.
  5. Leave the staff exactly where it is on B (on a peg or a firm stone), move the level beyond B, read B again as the new backsight, and carry on.

Book every reading at once in a table:

Point Backsight Foresight Rise Fall Height
A 2.33 100.00
B 0.87 1.24 1.09 101.09
C 2.15 1.28 99.81

Arithmetic check: (sum of backsights) − (sum of foresights) must equal (last height) − (first height). Here 3.20 − 3.39 = −0.19, and 99.81 − 100.00 = −0.19. If they differ, you have made an arithmetic slip.

Field check: always level back to where you started, by a different route if you can. The loop should close within about 2 cm per kilometre for careful work with a home-made level; much worse means a mistake, not bad luck — find it.

Over long sights the curve of the Earth matters: the true level surface falls away from a straight line of sight by about 7 cm at 1 km, but less than 1 mm at 100 m. Equal backsights and foresights cancel it.

Setting out a slope

A slope is written as a fall — "1 in 500" means 1 m down for every 500 m along (0.2 m per 100 m). Typical slopes:

Work Fall
Aqueduct or water channel 1 in 1,000 to 1 in 3,000
Irrigation channel 1 in 500 to 1 in 1,500
House drain, 10 cm pipe about 1 in 40
Road, comfortable for carts no steeper than 1 in 20

To lay out a channel at 1 in 1,000, set pegs every 20 m along the line, each 2 cm lower than the one before, with the level. Between pegs, use boning rods: three T-shaped sticks of exactly equal height. Stand two on pegs at the correct heights; sight across their tops and drive a third, in between, down until its top lines up too. Its foot is then exactly on the slope.

Angles and maps

The plane table is the easiest way to make an accurate map without any arithmetic. Fix a sheet of paper to a flat board about 60 × 50 cm on a steady tripod, and make an alidade: a straight ruler with a sight vane at each end.

  1. Measure a baseline — a straight, level line 100–300 m long — very carefully, twice, with the chain. Draw it to scale on the paper (for example 1 cm = 10 m).
  2. Set the table over one end of the baseline, level, and turn it so the drawn line points exactly along the real one.
  3. Lay the alidade against the pin at that point, sight each landmark (a tree, a hilltop, a house corner) in turn, and draw a ray toward it.
  4. Move to the other end of the baseline, line the table up again along the baseline, and draw rays to the same landmarks.
  5. Where the two rays to a landmark cross is its position on the map. Measure it with your scale.
  6. Check by drawing a third ray from a third point. If the three rays meet at a point, or in a tiny triangle, the work is good.

This is triangulation: from one measured line and a set of angles, you fix points you never walk to. Mapmakers chained one great baseline and then built networks of triangles from hilltop to hilltop across whole countries. With angles measured in degrees by a theodolite (Measuring Angles: Theodolite and Sextant) and tables of sines (see Geometry and Trigonometry), the sides can be calculated instead of drawn. A The Compass gives the direction of each line relative to north, which lets you survey a winding path or the inside of a tunnel by traverse — a chain of measured lines and bearings.

Measuring what you cannot walk

Width of a river (seen from above) Height of a tree Ttree on the far bank A Bstick C D 40 paces 40 paces From C, walk at right angles away from the river until stick B hides tree T. Mark D. C to D = A to T = the river's width 1.5 m 1.2 m 12 m ? Tree = 1.5 × 12 ÷ 1.2 = 15 m measure both shadows at the same moment
Fig. 3 Left: the width of a river by two equal triangles, with no arithmetic at all. Right: the height of a tree from two shadows measured at the same moment.

Width of a river. Stand at A, opposite a tree T on the far bank. Walk along your bank at right angles to AT for 40 paces; plant a stick B. Walk 40 paces more to C. Turn at right angles away from the river and walk until the stick B exactly hides the tree. Mark this point D. The triangles ABT and CBD are equal, so CD is the width of the river. Measure it.

Height by shadow. At the same moment, measure the shadow of the tree (or tower, or cliff) and the shadow of a stick of known height held upright. Height = stick height × object's shadow ÷ stick's shadow.

Height by the arm's-length stick. Hold a stick upright at arm's length so that the part above your fist equals the distance from your eye to your fist. Walk back until your fist lines up with the tree's foot and the stick's tip with its top. Your distance from the tree is then about its height.

Height of a hill. Level up it, step by step, as above — slow, but exact. Or measure the angle up to its top from both ends of a measured baseline and draw the triangle to scale.

How to tell it worked

  • Distances measured in opposite directions agree within 1 in 500 (20 cm in 100 m) or better.
  • A levelling loop closes within a few centimetres; the arithmetic check balances.
  • A building's diagonals are equal within 1–2 cm.
  • On a plane table, three rays to a point meet in a triangle smaller than a pencil dot.
  • The real test: water poured into the head of a finished channel runs the whole length at an even speed and does not pool or overflow anywhere.

Note Troubleshooting. Levelling loop won't close → a staff moved between foresight and backsight (always stand it on a peg or firm stone), the staff was not held vertical, or a reading was mis-booked (a classic error is 1.09 written as 1.90). Re-level the suspect stretch. Readings drift through the day → the tripod is sinking into soft ground or warming in the sun. Tread the legs in hard; shade the level. Water level gives different answers each time → an air bubble in the tube, or the tube was squeezed or stepped on. Refill it slowly; keep it in the shade so the water is the same temperature along its length. Chain measurements too long → the chain has stretched or a link has opened. Check it against your standard every week. Plane-table rays miss each other → the table was not lined up along the baseline at each station, or it turned while you worked. Clamp it firmly.

Dangers

Surveying itself is safe; its mistakes are not. A wrongly levelled aqueduct can waste years of a community's work, a drain laid with a backfall floods a house with sewage, and a foundation laid off-level cracks the walls above it. Check every result by a second, independent method before building on it.

Danger Tall poles, staffs and chains near overhead power lines kill. Once your community has electricity, or anywhere among old ruins with wires, never raise a staff or pole near a line. Lower poles and stop work in thunderstorms: a raised staff on an open hillside is a lightning rod.

  • Working along rivers, cliffs and quarry edges: watch your footing while looking through a sight. One person watches; one person sights.
  • Sunstroke on long days in open country: wear a hat and drink water (Surviving Cold and Heat).

What this unlocks

Surveying lets you bring water from a distant spring by Pipes, Plumbing and Aqueducts and aqueducts, take waste away by Sewers and Wastewater, lay out Irrigation and Canals and Locks, plan Roads and Bridges and Railways that climb gently, drive Mining and Tunnelling tunnels from both ends, and set square, level Foundations and Floors. Drawn up on paper, it becomes Maps and Mapmaking; refined with the The Telescope and accurate angles, it measured the size of the Earth itself (Astronomy).

How it was first done

Egyptian surveyors — the Greeks called them "rope-stretchers" — re-marked field boundaries with knotted cords after every Nile flood. The base of the Great Pyramid of Giza (about 2560 BC), 230 m on a side, is level to within about 2 cm and its corners are almost perfect right angles, probably laid out with water-filled trenches, plumb lines and stars.

In the 6th century BC the engineer Eupalinos dug a water tunnel 1,036 m long through a mountain on the Greek island of Samos, starting from both sides at once; the two teams met in the middle, probably within a metre in height. The Romans built their aqueducts, roads and city grids with the groma, the chorobates and the dioptra (a sighting instrument described by Hero of Alexandria in the 1st century AD), and some aqueducts fall only about 25 cm in each kilometre.

Edmund Gunter introduced his 100-link chain in England in 1620, and Willebrord Snellius in the Netherlands showed in 1615 how to measure long distances by a network of triangles. The theodolite (an angle-measuring telescope, see Measuring Angles: Theodolite and Sextant) grew from the 16th century onward. The Great Trigonometrical Survey of India, begun in 1802, carried chains of triangles from the southern tip of India to the Himalayas over half a century, and in the 1850s fixed the height of the mountain later named Everest — from more than 100 km away.